Energetics

Energetics

YEAR 2014

In October of 2014, by order of Zakład Wykonawstwa Sieci Elektrycznych Rzeszów Sp z o.o, we installed internal lighting of the newly expanded 220 KV distribution room in Stalowa Wola.

The project included:

  • laying down 1353 m of cable in metallized coating YKYFtly 0,6/1KV
  • installation of 130 and 180 VA isolation transformers, 9 in total
  • installation of foundations and steel lighting
  • poles, and wall brackets with lighting, 23 in total

We also prepared power supply and control of sliding door in the expanded part of 220 KV distribution room in Stalowa Wola. As a part of this task, we laid down metallized supply cables YKYFtly and YDY, and installed FB-100 control cabinet.

From January to April of 2014, by order of Commune of Niebylec, we performed lighting of national road No. 9 Radom – Rzeszów – Barwinek in towns of Baryczka and Połomia, and district road No. 1932 Jawornik – Gwoździanka in Jawornik

The project included:

  • construction of 2294 m of YAKY4x34 mm2 cable
  • installation of foundations and steel hexagonal poles – 29 in total
  • installation of Ambar 2 lighting fixtures with installation of light sources – 29 in total
  • installation of control cabinet for street lighting – 1 in total